Tyne Gangway completes F.A.T. for RACE BANK personnel transfer system.  Tyne Gangway has built a 25metre Walk to work system in record time.  The Gangway and Tower sections were built in a little over 4 weeks.

The full Design & Build process took 9 weeks in total.

The system will be installed onto an accommodation Jack-up vessel and used to aid installation of various equipment on the RACE BANK offshore Wind Turbine Project.

The Walk-to-Work system was designed to DNVGL-ST-0358 and is class approved.